Cardoner Group brings together its expertise in a strategic industrial wastewater treatment project
Ongoing project 08.07.26

Cardoner Group brings together its expertise in a strategic industrial wastewater treatment project

  • Constructora del cardoner
  • Oserma
  • Cardoner aigua
  • Delyproy cardoner
  • Depurnord cardoner
The expansion of the Peinaje del Llobregat Industrial Wastewater Treatment Plant highlights Cardoner Group’s ability to deliver integrated water solutions through the collaboration of four of its divisions.

Cardoner Group has commenced the expansion of the Peinaje del Llobregat Industrial Wastewater Treatment Plant (IWWTP), a strategic project led by Depurnord Cardoner that marks the first initiative jointly delivered by four divisions of the group: Depurnord Cardoner, Constructora del Cardoner, OSERMA and Delyproy.

edari-peinajes-aigua
The project brings together engineering, process design, mechanical installations and civil works within a single integrated structure, showcasing the synergies between Cardoner Group’s different divisions.

Commissioned by Urbaser, the project includes the expansion of the existing treatment plant through the construction of a new reception and pre-treatment area, new physico-chemical treatment systems, high- and low-load biological reactors, a membrane bioreactor (MBR) treatment system, a new sludge treatment line and several auxiliary facilities. All works will be carried out while the existing plant remains fully operational, requiring exceptionally precise planning and continuous coordination between the different project teams.

From a technological perspective, the upgraded plant will incorporate some of the most advanced solutions currently available for the treatment of industrial wastewater and leachates with varying characteristics, establishing itself as a benchmark project thanks to both its technical complexity and its ability to manage different types of industrial effluents using state-of-the-art treatment technologies.

edari-peinajes-civil-aigua

Depurnord Cardoner is leading the project, taking responsibility for engineering, process design and mechanical installations; Constructora del Cardoner is delivering the civil works; OSERMA is responsible for the civil engineering design; and Delyproy contributes its specialist expertise in metal fabrication as part of the project’s integrated delivery. This collaborative approach demonstrates Cardoner Group’s ability to coordinate multiple areas of expertise within a single organisation and provide comprehensive solutions tailored to each client’s specific needs.

With a budget exceeding €5.2 million and a 12-month construction programme, this development represents a strategic project for Cardoner Group and a clear example of the value created through collaboration between its different divisions. It is a delivery model set to become a benchmark for future industrial wastewater treatment projects.